Site Commissioning Assistance Request Form

Please complete the below form to request assistance.
Site Commissioning Assistance Request
Notes

Prior to the site attendance being called up:

  1. All fittings should have been connected for final 240v supply for a min of 24H
  2. A mains fail test should be conducted to verify operation
  3. All final supply boards with emergency subcircuits should have a ITU (Transponder) installed.
  4. All installed ITUs need to be connected together and to the System Control Unit (SCU)
  5. Final wiring is as per AS2293 with a separate active just for emergency supply, starting at the local DB & not shared with any other fittings.
  6. Final emergency actives start at their control circuit breaker and are not connected to any dimming controls

Once Received:

  1. CVG will contact you and advise of the next available site date.
  2. Contractor will advise on any specific access/induction requirements
  3. CVG will provide commissioning assistance to the project as per our stand. Commissioning Manual (available on request, email as per above.)
  4. The Contractor will be responsible for labelling fittings/provision of all access, including to luminaires (if required)
  5. CVG will attend site under the direct supervision of the Contractor, who will be responsible for any electrical works as may be required.

On completion of the site visit:

  1. CVG will provide a commissioning test report (as per our published manual) and a set of numbered drawings (if provided)
  2. CVG will update the site SCU with the newly installed fittings
  3. CVG will provide a fitting register for the new installed project
  4. CVG cannot provide certification of compliance to standards, that is work by others.

Company Details

CVG Lighting Pty Ltd
ABN: 26 112 054 823

Conditions of Sale

Contact Details

PHONE: +612 9708 4455
sales@cvglighting.com
Call Now

Office Location

Level 2, Suite 210, 29 Kiora Rd.
Miranda NSW 2228
Get Directions
map-marker